Brooklyn Multifamily Renovation Program

We carried out full gut renovations across one major client’s distressed Brooklyn brownstone and walk-up properties, generally four to eight units. We rebuilt interiors and replaced building systems as part of the owner’s value-add repositioning program.

Project facts

Location
Brooklyn, NY
Properties
Brownstones and walk-ups, generally four to eight units
Scope
Full gut renovations and replacement building systems

Full Gut Renovations Across a Brooklyn Portfolio

One Client’s Brooklyn Renovation Program

The owner acquired these distressed properties for value-add repositioning.

Rebuilding Interiors and Replacing Building Systems

We stripped out the old interiors, then rebuilt the living spaces with new plumbing, electrical, and mechanical systems and finishes.

Cost and Schedule Comparisons

The figures describe historical construction results from one client’s Brooklyn renovation program.

Results for This Client’s Program

26%

Cost Savings

In this client’s comparison of projects under 5,000 square feet

53%

Projects Completed Early

In this client’s broader program, by an average of three months

Construction Costs

The client compared construction costs on similar renovations completed by Bau and other contractors in its program.

Less per Square Foot
$46Average savings in the client comparison
Total Project Cost Savings
Roughly 20%Overall savings in the client comparison

Under 5,000 square feet

Construction cost per square foot

Other contractors
$255/SF
Bau Builders
$189/SF

Over 5,000 square feet

Construction cost per square foot

Other contractors
$209/SF
Bau Builders
$181/SF

Project Schedules

We compared actual completion times for ten properties in the client’s program with their underwritten schedules. These properties are a sample of the broader program results behind the 53% early-completion figure.

Positive time savings mean a project finished ahead of its underwritten schedule. Zero means it finished on time. A negative value means it took longer.

Ten-property schedule sample. Durations and time savings are in months.
PropertyProject sizeUnderwritten completion
months
Actual completion
months
Months saved
Property 1$910k94+5Ahead of schedule
Property 2$600k73.5+3.5Ahead of schedule
Property 3$445k52+3Ahead of schedule
Property 4$760k68-2Later than underwritten
Property 5$725k660On time
Property 6$680k64+2Ahead of schedule
Property 7$975k65+1Ahead of schedule
Property 8$450k660On time
Property 9$860k63.5+2.5Ahead of schedule
Property 10$430k53+2Ahead of schedule

Discuss Your Multifamily Renovation

Talk with us about renovating your multifamily property. We can discuss the existing building, construction options, budget, and schedule.